№ files_lp_4_process_2_66974
File format: docx
Character count: 353980
File size: 569 KB
Comprehensive reference source detailing the chronological steps, requirements, and processes for generator interconnection and deliverability assessment, including study tracks, interconnection request validation, and coordination with affected systems.
Year:
2019
Region / Organization:
CAISO (California Independent System Operator)
Document Type:
Business Practice Manual
Owner / Author:
Stephen Rutty, Director, Grid Assets
Approval Date:
08/28/2013
Effective Date:
08/28/2013
Revision History:
Versions 1.0–19.0 with updates on interconnection processes, deliverability status, study procedures, and energy storage integration
Intended Audience:
Interconnection Customers, Grid Operators, and Transmission Owners
Scope:
Generator interconnection and deliverability allocation procedures under CAISO Tariff Appendix DD
Related Resources:
CAISO Queue, Resource Interconnection Management System (RIMS), Study Tracks
Price: 8 / 10 USD
The file will be delivered to the email address provided at checkout within 12 hours.
The file will be delivered to the email address provided at checkout within 12 hours.
Don’t have cryptocurrency yet?
You can still complete your purchase in a few minutes:- Buy Crypto in a trusted app (Coinbase, Kraken, Cash App or any similar service).
- In the app, tap Send.
- Select network, paste our wallet address.
- Send the exact amount shown above.
The final amount may vary slightly depending on the payment method.
The file will be sent to the email address provided at checkout within 24 hours.
The product description is provided for reference. Actual content and formatting may differ slightly.
Year:
2020
Note:
Region / City
Topic:
Interconnection and Deliverability Allocation Procedures
Document Type:
Business Practice Manual
Organization:
CAISO
Author:
Stephen Rutty
Target Audience:
Interconnection Customers, Grid Operators
Effective Date:
08/28/2013
Approval Date:
08/28/2013
Revision History:
Last revised on 11/24/2020
Date of Changes:
11/24/2020
Version History:
Version 25.0, Version 24.0, Version 23.0, etc.
Interconnection Process:
Detailed Chronological Sequence
Year:
2022
Region / City:
California, USA
Subject:
Generator interconnection and deliverability allocation
Document Type:
Business Practice Manual
Organization / Institution:
CAISO (California Independent System Operator)
Author:
Stephen Rutty
Author’s Title:
Director, Grid Assets
Approval Date:
09/08/2013
Effective Date:
09/08/2013
Last Revision Date:
07/29/2022
Version:
30.0
Revision History:
Detailed updates from Version 1.0 (07/26/2013) through Version 30.0
Target Audience:
Interconnection customers, transmission operators, and CAISO staff
Scope:
Procedures and guidelines for generator interconnection requests, study processes, deliverability allocation, and associated financial and operational requirements
Context:
Chronologically details the steps, requirements, and study processes for connecting generators to the grid, including regulatory compliance, study deposits, interconnection agreements, and deliverability status.
Year:
2025
Region / City:
Southern California
Topic:
Distributed Generation Deliverability
Document Type:
Application
Author:
Southern California Edison
Target Audience:
Distributed Generation Facility Owners, Utility Operators
Period of Validity:
Until April 15, 2025
Approval Date:
Not specified
Modification Date:
Not specified
Description:
Application for deliverability status submission for distributed generation facilities seeking interconnection to investor-owned utility distribution facilities under ISO Tariff Section 40.4.6.3.
Year:
2024
Region / City:
CAISO Controlled Grid
Theme:
Energy Transmission, Interconnection Procedures, Resource Adequacy
Document Type:
Appendix to the CAISO Tariff
Agency / Institution:
CAISO
Author:
Not specified
Target Audience:
Interconnection Customers, Load Serving Entities
Validity Period:
2024-2025
Approval Date:
Not specified
Amendment Date:
Not specified
Note:
Contextual Description
Year:
2023
Region / City:
California, US
Subject:
Energy Infrastructure Interconnection, Queue Management
Document Type:
Technical Guidelines / Tariff Commentary
Organization / Institution:
California Independent System Operator (CAISO)
Audience:
Generating Unit Owners, Interconnection Customers, Transmission Operators
Relevant Sections:
Tariff 2525.5.2, Appendix DD 6.7.2.3, Sections 6.7.2.7, 8.9.9, 11.3.2
Deposits and Fees:
$50,000 for repowering requests, $310,000 for modification assessments
Timeline Requirements:
45–60 calendar days for standard assessments, up to 120 days for certain network changes
Modification Types Covered:
Repowering, downsizing, capacity reallocation, deliverability transfers
Associated Agreements:
Generator Interconnection Agreement (GIA), LGIA, SGIA
Deadline Dates:
November 30 for downsizing requests
Assessment Procedures:
Written notice, technical data submission, deposit payment, CAISO response
Year:
2020
Note:
Region / City
Topic:
Interconnection and Deliverability Allocation Procedures
Document Type:
Business Practice Manual
Organization:
CAISO
Author:
Stephen Rutty
Target Audience:
Interconnection Customers, Grid Operators
Effective Date:
08/28/2013
Approval Date:
08/28/2013
Revision History:
Last revised on 11/24/2020
Date of Changes:
11/24/2020
Version History:
Version 25.0, Version 24.0, Version 23.0, etc.
Interconnection Process:
Detailed Chronological Sequence
Year:
2022
Region / City:
California, USA
Subject:
Generator interconnection and deliverability allocation
Document Type:
Business Practice Manual
Organization / Institution:
CAISO (California Independent System Operator)
Author:
Stephen Rutty
Author’s Title:
Director, Grid Assets
Approval Date:
09/08/2013
Effective Date:
09/08/2013
Last Revision Date:
07/29/2022
Version:
30.0
Revision History:
Detailed updates from Version 1.0 (07/26/2013) through Version 30.0
Target Audience:
Interconnection customers, transmission operators, and CAISO staff
Scope:
Procedures and guidelines for generator interconnection requests, study processes, deliverability allocation, and associated financial and operational requirements
Context:
Chronologically details the steps, requirements, and study processes for connecting generators to the grid, including regulatory compliance, study deposits, interconnection agreements, and deliverability status.
Year:
2017
Region / City:
Miami, FL
Subject:
Lease of parking spaces
Document Type:
Solicitation Notice
Organization:
Department of Veterans Affairs
Author:
Department of Veterans Affairs
Target Audience:
Property owners, brokers, and legal representatives
Period of Action:
Up to 5 years
Approval Date:
March 2017
Modification Date:
March 2017
Year:
2025
Jurisdiction:
Commonwealth of Massachusetts
Issuing authority:
Executive Office of Health and Human Services, Office of Medicaid (MassHealth)
Document type:
Nursing Facility Bulletin
Bulletin number:
190
Date issued:
January 2025
Supersedes:
Nursing Facility Bulletin 181 (September 2023)
Subject:
Use of CMS OBRA MDS 3.0 assessments for nursing facility fee-for-service payments
Program:
MassHealth
Regulatory framework:
CMS OBRA MDS 3.0, Resident Assessment Instrument Manual
Target audience:
Nursing Facilities Participating in MassHealth
Author:
Mike Levine, Assistant Secretary for MassHealth
Effective date:
January 21, 2025
Assessment system referenced:
Minimum Data Set (MDS) 3.0
Payment methodology:
Patient Driven Payment Model (PDPM)
Reporting requirements:
Submission of MDS assessments to CMS and MassHealth
Compliance requirements:
Inclusion of MassHealth provider ID and MassHealth member ID on MDS assessments
Year:
1901
Compilation number:
190
Compilation date:
22 January 2026
Includes amendments:
Act No. 1, 2026
Jurisdiction:
Commonwealth of Australia
Subject matter:
Customs law; antidumping and countervailing duties
Type of document:
Consolidated statute compilation
Volumes:
5 volumes
Register:
Federal Register of Legislation
Related legislation:
Legislation Act 2003
Administering authority:
Minister responsible for customs and trade matters
Administrative body:
AntiDumping Commission
Commencement status:
In force as at 22 January 2026
Year:
1936
Jurisdiction:
Australia
Type of document:
Legislation
Amendments included:
Act No. 9, 2025
Compilation date:
1 January 2026
Volumes:
7
Sections covered:
178A–468, Schedules, Endnotes
Editorial authority:
First Parliamentary Counsel
Legislation history:
Detailed in endnotes 3 and 4
Self-repealing provisions:
Noted in endnotes
Uncommenced amendments:
Indicated in endnotes
Application, saving and transitional provisions:
Referenced in endnotes
Context:
Legislative source detailing the text, amendments, and endnotes of the Income Tax Assessment Act 1936 as compiled and in force on 1 January 2026, including historical and editorial notes.
Year:
2021
Region / City:
Not specified
Topic:
Service Assurance, Trouble Ticketing, API Certification
Document Type:
Certification Report
Organization:
BMC Software
Author:
BMC Software
Target Audience:
Communications Service Providers (CSPs), Network Operators, API Developers
Effective Period:
Not specified
Approval Date:
27/10/2021
Modification Date:
Not specified
Year:
2021
Report Date:
10 October 2021
Organization:
TM Forum
Company:
Sterlite Tech
Product:
Unified Product Catalog (UPC)
Portfolio:
STL Digital BSS
API Name:
Product Offering Qualification API TMF679
API Release Version:
19.0 / v4.0
Document Type:
Conformance Certification Report
Technology Domain:
Telecommunications Software and Open APIs
System Architecture:
Open Digital Architecture (ODA)
Implementation Model:
Microservices
Supported Standards:
TM Forum Open APIs
Related APIs:
Product Catalog (TMF620); Customer Management (TMF629); Account Management (TMF666); Payment Management (TMF676); Customer Bill Management (TMF678); Product Inventory (TMF637); Product Ordering (TMF622); Quote Management (TMF648); Self Care (TMF910); Communication Management (TMF681); Service Order (TMF641); Service Configuration and Activation (TMF640); Service Inventory (TMF638); Service Catalog (TMF633); Usage Management (TMF635); Prepay Balance Management (TMF654)
Industry:
Telecommunications
Purpose:
Certification of conformance for implementation of the Product Offering Qualification API within the STL Unified Product Catalog platform
Functional Scope:
Product offer eligibility validation, rule-based qualification checks, and contextual retrieval of eligible product offerings
Target Users:
Telecommunications operators and partner application systems